Skip to content
SkillPass

Lessons Learned: Meaning, Process, Questions and Template

Lessons learned are the insights a team records from a project so the next one goes better: what worked, what did not and what to do differently. The process has five steps: collect, write down specifically, analyze, store and apply in the next project. Most lessons learned do not fail at collection. They fail because nobody reads them again, or because the person who learned the most left before the meeting.

Author: Kevin Baur BSc

Published on

Contents
Title card: lessons learned, what went well and what went wrong, with meaning, five steps, questions and a template

At the end of a project the team gathers, fills a wall with sticky notes and agrees: next time we talk to IT earlier. Six months later the next project starts and nobody remembers the note. This guide explains the term and how it differs from similar formats, walks you through five steps to lessons that actually get used, and gives you questions and a template to copy.

What does lessons learned mean?

Lessons learned (British English: lessons learnt) are experiences distilled from past activities that should be taken into account in future actions. The Project Management Institute defines them as the knowledge gained during a project which shows how project events were addressed or should be addressed in the future, for the purpose of improving future performance.

A stricter definition is used by the space agencies NASA, ESA and JAXA: a lesson learned is knowledge or understanding gained by experience, from a success as much as from a failure. To count, it has to meet three conditions:

  • Significant: it has a real or assumed impact on operations.
  • Valid: it is factually and technically correct.
  • Applicable: it identifies a specific design, process or decision that reduces the chance of failure or reinforces a positive result.

These three tests help later when you analyze what you collected. They also show the difference from project documentation: documentation describes what happened, a lesson learned says what you will do differently. That makes them one of the simplest methods in knowledge management: they are tied to a date that exists anyway.

Lessons learned vs retrospective, after action review and post mortem

Many teams run lessons learned under another name. The formats differ in timing and goal.

Four formats for learning from experience
FormatWhenFocusOutput
Lessons learnedAt project close, in larger projects also after phases and milestonesGood and bad, for future projectsInsights and recommendations, stored for people who were not there
Retrospective (Scrum)At the end of every sprintHow the team workedImprovements for the next sprint
After action reviewRight after an action or event, often shortIntended versus actual, the participants' own actionsLessons the participants take forward themselves
Post mortemAfter a failure or significant downtimeCauses of a problemMeasures so it does not happen again

Retrospective: the Scrum Guide describes the sprint retrospective as the event that concludes each sprint. The team inspects how the sprint went with regard to individuals, interactions, processes and tools, what went well, what problems it encountered and how they were or were not solved. For a one month sprint it is timeboxed to three hours, and the most impactful improvements are addressed as soon as possible.

After action review: developed by the U.S. Army, it starts with a clear comparison of intended and actual results. Assigning blame is antithetical to its purpose, and each participant looks at their own actions.

Post mortem: it looks for the causes of a failure or outage, while a retrospective reviews positive and negative things alike. Wikipedia notes that the PMBOK refers to the process as lessons learned.

The key difference: a retrospective improves the work of the same team in the next sprint. Lessons learned are meant to help people who were not on the project, which is why writing them down and storing them matters so much.

When to capture lessons learned

  • At project close: the classic moment, often as part of the closing report.
  • After phases and milestones: in longer projects. Asana recommends sending the survey right after the project or at the end of a significant phase, while memories are fresh.
  • At the start of a new project: this is where lessons are used, not collected. Make reading the lessons of similar past projects part of every kickoff.
  • Before a key person leaves the project: the moment most often missed. Whoever leaves mid project takes their view with them, and it is missing at the closing session.

The lessons learned process in 5 steps

The steps follow the cycle Asana describes: identify, document, analyze, store and retrieve.

1. Collect experiences

A short survey followed by a meeting works well. Asana advises choosing a facilitator who is not the project manager so team members feel comfortable speaking freely. For planning, Atlassian's retrospective play gives a useful benchmark: about 15 minutes of preparation, 60 minutes of meeting, 4 to 8 people.

2. Write them down specifically

"Improve communication" is not a lesson, it is a wish. A useful lesson describes the situation, what happened, why it happened and what will be different next time. For example: "In projects with new software, involve IT in week one, because otherwise access approvals delay the start." Record what went well too. Under the NASA, ESA and JAXA definition, successes count as much as failures.

3. Analyze and condense

Merge duplicates and test each item against the three questions: significant, valid, applicable? Atlassian advises against dwelling on one time mistakes or successes that will not affect future work. A few lessons that change something are the goal.

4. Store them where others look

A lesson in someone's personal folder is lost to the next team. Keep lessons learned in one fixed place, such as a project database or a shared drive, and tag them by project type, topic and department.

5. Apply them in the next project

The step most often skipped. Every lesson needs an owner and a place where it changes something: a checklist, a project template, a standard operating procedure or your process documentation. Only when the lesson sits where the work happens does it become a better way of working.

Lessons learned questions

The core is three questions that Asana also names: What went well? What went wrong? What could be improved? A variant from retrospectives is the 4Ls method: what did the team love, loathe, learn and long for? For a whole project it pays to dig deeper:

  • Did we reach the goal? Where does the result differ from the plan, and why?
  • Which decision would we make differently today?
  • Which assumption at the start turned out to be wrong?
  • What knowledge did only one person have, and where is it written down now?
  • What should the next team know first?
  • Which of these go into templates, checklists or processes, and who takes care of it?

Lessons learned template

Copy the table into your document or spreadsheet. Above it, add project name, period, participants, date and facilitator. The two rows are made up examples that show how specific an entry should be.

Lessons learned template: one row per lesson
No.SituationWhat happened?CauseLesson and recommendationOwnerApplied in
1Rollout of a new point of sale systemStart delayed by two weeksAccess requested only in the launch weekRequest access four weeks before launchProject leadProject start checklist
2Training for the storesShort videos instead of classroom sessions, few follow up questionsStaff could learn at their own paceOffer short videos first in future trainingsPeople developmentTraining plan template
3

The last column matters most. If it stays empty, the lesson has been written down but not yet learned.

Common mistakes

  • Looking for someone to blame: once blame is in the room, people say only what they must. In an after action review, blame explicitly defeats the purpose.
  • Staying vague: "plan better" changes nothing. Every lesson needs a concrete recommendation.
  • Storing without applying: without step 5 the archive is a graveyard of good intentions.
  • The key people are missing: whoever left the project early is not in the room, and with them the experience from the hardest phases.

When the experience walks out the door

Lessons learned capture what a team learned together from a project. They do not capture how one person does their job: the trick in the billing run, which supplier calls back on which channel, which exceptions exist. That knowledge is often tacit knowledge, and it rarely comes up in a workshop by itself.

When a key person leaves the company, a lessons learned session is not enough. You need a proper knowledge transfer and an employee handover document for the successor. If someone leaves mid project, add a short one to one conversation before their last day: What would you advise your successor on this project? Which decisions are open? Who do they need to know? That is different from an exit interview, which is about the reasons for leaving.

Conclusion

Lessons learned are quick to collect and quick to forget. To work, they need specific wording, a fixed place and above all step 5: an owner who takes each lesson to where the work happens. Schedule the session while everyone is still there, ask about the good and the bad, and remember the people who left the project before the end. Otherwise their experience never makes it into the closing workshop.

Frequently asked questions

What is the meaning of lessons learned?
Lessons learned are the knowledge gained from a project or activity, positive or negative, recorded so that future work goes better. The term also refers to the method and to the meeting where the lessons are collected.
What is the difference between lessons learned and a retrospective?
A retrospective takes place at the end of every sprint in Scrum and improves the work of the same team in the next sprint. Lessons learned are usually captured at project close or after phases and are meant to help other teams and future projects.
When should you hold a lessons learned meeting?
Right after the project or at the end of a significant phase, while memories are fresh. If a key person leaves the project early, capture their view before their last day.
Who should attend a lessons learned session?
Everyone who carried the project. Ideally the facilitator is not the project manager, so people speak freely. As a benchmark, Atlassian suggests 4 to 8 people and about 60 minutes for a retrospective.
How do you document lessons learned?
Use one row per lesson with the situation, what happened, the cause, the recommendation, an owner and where the recommendation is applied, such as a checklist or template. Store it in one fixed place with tags so the next team can find it.

Sources

Back to overview